Avoid Costly Grid Upgrades with Energy Storage Incentives in BC

This project uses a battery energy storage system (BESS) to help a facility avoid costly power infrastructure upgrades. By strategically managing energy use, it reduces peak demand on the grid and participates in the BC Hydro ESI program for cost savings.

Project Background

The BC Hydro Energy Storage Incentive (ESI) program played a crucial role in enabling this project to implement a Moment Energy battery energy storage system (BESS). By financing 80% of the project cost, the ESI program facilitated the customer’s ability to adopt energy storage technology and reduce their energy costs.

Limited Transformer Capacity

The site's current power capacity is 1250 kW, with plans to upgrade to 1750 kW. However, the remaining 56 kWh (56 kVA) capacity is a major obstacle to electrification. Upgrading transformer capacity can take multiple years, adding further delays to meeting the site's power needs.

Peak Demand for Electricity

To participate in BC Hydro's Energy Storage Incentive (ESI) Program, the customer needed a BESS capable of shifting or shedding loads to reduce constraints on the grid during winter months.

Solution

Moment Energy’s Luna BESS provides clean, affordable, and reliable power.

750 kVA BESS

Moment Energy recommended a 750 kVA BESS, with 400 kVA nominated for the BC Hydro ESI program and the rest for the customer's operations.

Energy Management System

The Luna BESS was integrated with an EMS to support the facility's two MVA transformer and manage participation in demand response events.

Remote Support & Maintenance

Moment Energy will provide ten years of remote support and maintenance for the Luna BESS, ensuring its optimal performance and reliability.

BC Hydro ESI Program Benefits

The BC Hydro Energy Storage Incentive (ESI) program played a crucial role in enabling this project to implement a Moment Energy battery energy storage system (BESS). By financing 80% of the project cost, the ESI program facilitated the customer’s ability to adopt energy storage technology and reduce their energy costs.

80%

Project Cost Funded by BC Hydro

Participation in the BC Hydro ESI Program resulted in significant cost reduction for the project. The customer received financial incentives for nominating capacity to reduce loads from the BC Hydro grid during the winter months.

750 kVA

Additional Power

The Luna BESS deployment provided an additional 750 kVA of available power, addressing the transformer capacity constraint and facilitating future electrification efforts at the facility.

10 years

Project Life

To participate in these demand response calls, BC Hydro signs a 10 year contract with the customer to determine the capacity nominated for use of the batteries, and the incentives will apply accordingly.

Speak with our team today

For general inquiries or to learn more about our services, please fill out the form.

Industry Applications

Thank you! Your submission has been received.
Oops! Something went wrong while submitting the form.

Let's discuss your energy needs

Fill out the form below, and our team will reach out via email to explore how we can meet your specific energy storage requirements. During our conversation, we’ll provide access to our technical specifications and answer any questions.

Please note, Moment Energy’s battery energy storage systems start at a minimum project size of 400 kWh.

Industry Applications

Thank you! Your submission has been received.
Oops! Something went wrong while submitting the form.
Thank you! Your submission has been received.
Oops! Something went wrong while submitting the form.